Wikipedia defines electric power transmission is the bulk transfer of electrical power (or more correctly energy), a process in the delivery of electricity to consumers. A power transmission network typically connects power plants to multiple substations near a populated area. The wiring from substations to customers is referred to as Electricity distribution, following the historic business model separating the wholesale electricity transmission business from distributors who deliver the electricity to the homes.[1] Electric power transmission allows distant energy sources (such as hydroelectric power plants) to be connected to consumers in population centers, and may allow exploitation of low-grade fuel resources such as coal that would otherwise be too costly to transport to generating facilities. Usually transmission lines use three phase alternating current (AC). Single phase AC current is sometimes used in a railway electrification system. High-voltage direct current systems are used for long distance transmission, or some undersea cables, or for connecting two different ac networks. Electricity is transmitted at high voltages (110 kV or above) to reduce the energy lost in transmission. Power is usually transmitted as alternating current through overhead power lines. Underground power transmission is used only in densely populated areas because of its higher cost of installation and maintenance when compared with overhead wires,and the difficulty of voltage control on long cables. A power transmission network is referred to as a “grid”. Multiple redundant lines between points on the network are provided so that power can be routed from any power plant to any load center, through a variety of routes, based on the economics of the transmission path and the cost of power. Much analysis is done by transmission companies to determine the maximum reliable capacity of each line, which, due to system stability considerations, may be less than the physical or thermal limit of the line. Deregulation of electricity companies in many countries has led to renewed interest in reliable economic design of transmission networks. However, in some places the gaming of a deregulated energy system has led to disaster, such as that which occurred during the California electricity crisis of 2000 and 2001.[2]
America’s infrastructure is changing in ways that its designers never anticipated. Distributed and intermittent electricity generation, such as wind power, is rapidly expanding, new smart meters are giving consumers more control over their energy usage, and plug-in hybrid electric vehicles may someday radically increase the overall demand for electricity. The evolution of America’s energy needs has forced scientists and engineers to re-examine the operations, efficiency and security of the national power grid. The creation of a more secure and efficient national power grid requires significant innovations in the way we transmit electricity and monitor its use. To better assess the challenges facing the power grid, the U.S. Department of Energy’s (DOE) Argonne National Laboratory hosted a workshop that brought together power system and modeling experts from federal agencies, national laboratories and academia. “Modeling and simulation have proved to be effective tools for the power industry on many levels,” said Mark Petri, Argonne’s technology development director and one of the workshop’s organizers. “We need to develop a comprehensive and integrated approach that will enable us to better understand the full implications of an evolving power grid as we plan for future demand and power sources.” The workshop centered on the need for new methods to simulate the national power grid by modeling the creation and flow of electric power as well as the grid’s connection to other critical infrastructures, such as transportation, gas, water and communications. Through detailed simulations of how electric power is supplied and transferred around the country, researchers can bolster not only the grid’s security but also its reliability, efficiency and resiliency. “Implementing smart grid technologies on a large scale will not be trivial,” Petri added. “The challenges go beyond technical and economic issues. The smart grid technologies could fundamentally change how national power grid systems operate and respond to disruptions.” Because of the great diversity of ways in which electricity is created, distributed and consumed, engineers face a challenge in creating reliable models of large power networks. They have to deal with the intermittent nature of some of the sources (like wind or solar), optimize how power is transmitted and balance economic, security and environmental priorities when finding solutions. “In the short-term,” Petri said, “these simulations could help devise ways to solve the problem of grid congestion, which currently costs consumers many hundreds of millions of dollars each year. Even small improvements in grid efficiency that better models and simulations would produce would make the investment cost-effective.” The workshop, which was sponsored by U.S. Department of Homeland Security Science and Technology Directorate, identified barriers that a national grid simulation capability would need to overcome to be effective. The findings of the workshop appear in the report “National Power Grid Simulation Capability: Needs and Issues.” According to Petri, an operational plan for a national power grid simulation capability that engages industry to better understand their needs, capabilities and concerns would support a more secure and reliable electric power grid system for the future. SOURCE: DOE/Argonne National Laboratory
Wind is not only a good, clean source of energy, it’s also a way of generating more power quickly. Unlike a nuclear plant that would take anywhere from 10 to 15 years to go online, a wind farm can be up and running in as little as two years. And with the incentives for renewable energy that are part of the economic stimulus bill passed by the Senate in February ─ including a $7 billion renewable energy loan guarantee program, tax credits and extended bonus depreciation ─ wind energy is a power source that makes economic sense. It is true that the recent crisis in the financial markets has made banks more cautious about lending, requiring developers to provide 1.5 to 2 years worth of data in their loan applications. However, this delay in the financing process is mitigated by the fact that turbine manufacturers now have sufficient inventory to fill orders. To make a long story short ─ it’s a good time to look into wind power. Building and maintaining a relationship with the utilityOnce it has been determined that “building” a wind farm in a particular location makes sense, connecting it with the existing transmission system is the key challenge electrical engineers have to tackle. The system must be designed so a single component failure or outage does not impact the rest of the system. It must also be compatible with other stations owned by the host utility to ensure that maintenance personnel are familiar with basic operating functions and do not have to be retrained. The developer’s station needs to meet the bulk power design requirements up to the point of voltage transformation that takes place at the demarcation line between developer and utility. Every utility has specific design requirements, both for the physical design and CAD drawing format. Establishing a design protocol up front helps avoid duplicating efforts. Simple matters such as switch numbering, protection and communication software and hardware design can become costly issues if they are not addressed early on in the process. To ensure good collaboration, detailed task responsibilities should cover areas like relay settings, SCADA and security. If the developer is providing the design of the new substation or the retrofit of the existing point of interface station, all documents and drawings must be submitted for approval. The same applies to primary equipment specifications and purchases. The utility should also be kept up to date on project schedule and milestone points for drawing approval and commissioning testing. When drawing up a project schedule, keep in mind that before the station is energized, the utility field personnel is likely to want to witness or even perform itself all relay, metering and communications equipment tests. Designing the new substationSome utilities have the capability to design and build the station, others prefer to outsource. In either case, the design of the station will depend on the topology of the site, equipment rations, and utility requirements in the given service area. Since the substation that ultimately connects the wind park generation to the high voltage grid is designed to be part of the overall interconnected system it needs to meet its overall requirements. Equipment ratings are influenced more by the through power flows than by the output of the wind park, since the utility would not want the point of interconnection (POI) station to limit ratings for the adjoining networks. Requirements for utility point of interconnection substations vary according to region and utility. If the POI falls into the bulk power transmission category, design criteria must fit the reliability requirements set by the National Electric Reliability Corporation as well as the regional reliability authority, for example the Northeast Power Coordinating Council or the Southern Electric Reliability Corporation as well as those established by the respective utility. Bulk power classification is determined by the way the transmission line is used to transfer power within the network. Unless the wind park is located next to a utility transmission line, it is most economical to convert the wind park output to a higher voltage and transmit power via overhead transmission lines to the POI near an existing line. Since the latter is owned and operated by the developer, its construction is typically not subject to utility approval, unlike the line construction, which is regulated by state and local government agencies. Keep in mind that the extent of the regulations can vary and depend on the voltage level as well as the length of the transmission line. Fiber optic interconnections: The devil is in the detailsIn a typical wind park, turbines are connected by fiber optics networks at three points: the turbine, the meteorological tower(s), and at the substation control module. Via these fiber optics systems, turbines communicate with a centrally located wind park management system that is located in the wind park substation. The technology used to establish this connection is proprietary to the turbine manufacturer. Depending on the size of the wind park the meteorological (MET) tower also communicates with the management system that tells the controller which direction turbines need to move in and at what pitch they need to move to provide optimum energy generation under real time wind conditions. In other words, the turbines are in constant two-way communication with the management system relaying data such as generation, power factor, alarm status, and SCADA information. With underground installations, the fiber optic cable is typically bedded above the three phase power cables in a common trench. In overhead installations, it is lashed to a messenger that is strung underneath the power cables. In the event that the cables need to be placed in duct work, for example in the event of a direction drill underneath the highway, the fiber optic network receives its own conduit. The key to a successful fiber optic network is to create a minimum number of splices. Each splice introduces decibel losses into the system. While it is tempting to splice the cable whenever the power cable needs to be cut, a dynamic and cooperative relationship between the engineer and the contractor can eliminate or re-route the network in the field in a way that greatly reduces signal losses. It is also important to note that reel management of the fiber optics during installation is critical and will result in faster, more efficient, and more economical installation. Complying with transmission system protection requirementsFederal and regional regulators require bulk power transmission lines to feature redundantly designed and installed protection systems. Their goal is to prevent a single point of failure from downing the entire system. To create this redundancy, each protection system must be based on a different principle and it is generally supplied by a different manufacturer. To give an example: System A could be a directional comparison blocking scheme over power line carrier while System B would be permissive overreaching transfer trip scheme communication over telephone circuits. Ultimately, the host utility will provide its protection standards and help decide which schemes will work best. Before any scheme can be designed, however, the engineering team and the utility need to assess available communication possibilities. Ideally, one of the systems would be a fiber optic link installed on optical ground wire cable — which is installed in the shield wire(s) at the top of the structure to provide protection for the transmission from lightning strikes — if that can be designed economically. Other viable options are power line carriers, T1 lines and microwave. Each protection system should also be connected to dedicated current transformers and voltage transformers. Exceptions can be made in the case of a single voltage transformer with independent secondary windings. The DC tripping systems also need to be independent. This requires dual batteries, chargers, trip coils, and source of station service. Oftentimes, a backup generator is required to provide continuity in the event of power loss at both station service supplies. Regulators also stipulate a physical separation of the two systems. Typically, relay and communication panels are separated in the control house, sometimes in different rooms. All cabling needs to be separated into independent raceways and conduits. Ultimately, the independent protection systems trip the same circuit breaker. Still, breaker failure protection is required, isolating the failed breaker locally and remotely tripping the backup breakers. OutlookA record-shattering year for the wind industry, in 2008 more than 8,300 megawatts of new wind energy were brought online. In addition, 55 new wind-related manufacturing facilities were opened, expanded, or announced. Given the political will to make renewable energy the energy source of choice, the wind industry is in an excellent position to contribute to the nation’s economic recovery and to reduction of carbon emission’s necessary to deal with global warming. Author: Brook Knodel is Deputy Engineering Manager – Electrical with Careba Mott MacDonald (CMM) an engineering firm which specializes in design of major power generation projects — including wind power, biomass, biodiesel and coal fired plants — plus distribution and transmission projects for power plant operators, power plant developers, industrial facility operators, equipment manufacturers, contractors and power distribution utilities. Based in Westwood, Massachusetts, CMM is a division of Mott MacDonald, a global engineering and consultancy firm delivering solutions in energy, transportation, construction, water and environment.
I would like to thank the scientists in various fields of endeavor, who helped me along the way with their research and writing and their wisdom. I have named a few and some others will know who they are without any recognition from me, and these men have gained my respect as well. We must do what we can to update our power grid in this country or we will not survive our climate crisis. I’ll see you around the galaxy…